Chip Sealing Twp Roads / Drainage Culvert Lining
Starting week of 8/22 and 8/29 the following roadways will be undergoing chip sealing:
Barley Sheaf Rd., Locust Rd., Roosevelt Rd., Lazy Brook Rd., Aray Dr.
Minimal delays should be expected as this is a fast process. Roads may be driven over within moments of the process being completed. A few weeks after this process is complete, we will return to sweep the access stone from these roadways.
Starting 8/8, work will begin on Horseshoe Dr. with lining the drainage culvert and will take approx. 2 weeks to complete. The roadway will remain open, and no delays should be expected in this area.